Introduction to project management/IPM103/Resources/Glossary
From WikiEducator
- Alternative analysis
- An estimating technique that includes several solutions to complete the same task.
- Bottom-up estimation
- Breaking all tasks down to their small packages to estimate the resources required for each.
- Crashing
- Adding more resources to a task, in order to speed up the activity.
- Effort based activities
- When applying more effort will result in the task being completed quicker.
- Expert Estimation
- Using an expert to provide estimates of the resource requirements for a project. For example, a quantity surveyor.
- Fixed duration activities
- When no matter what resources you add the activity will still take the same time. For example, the time taken for paint to dry.
- Law of diminishing returns
- When adding resources reaches a point when the output does not increase proportionally. For example, when you have so many people working on one task that they start getting in each other's way.
- Published estimating data
-
- Using published estimation guides to estimate resource requirements.
- Resource calendar
- A calendar that shows the availability of resources over time.
- Resource Requirements
- The number and type of resources required to complete all the tasks in a project.