Introduction to project management/IPM103/Budget/Methods quiz
From WikiEducator
Jump to: navigation, search
Quiz
Test out what you have learnt in this fun quiz.
- Which of the following methods is associated with reorganising estimates by grouping with activity codes?
- Analogous
- Incorrect try again
- Parametric
- Incorrect try again
- Bottom-Up
- Incorrect try again
- Activity-Based
- Correct well done
- Analogous
- Which of the following methods is associated with an estimate that is based on other project estimates?
- Analogous
- Correct good job
- Parametric
- Incorrect try again
- Bottom-Up
- Incorrect try again
- Activity-Based
- Incorrect try again
- Analogous
- Which of the following methods is associated with identifying the cost of each item in each activity of the project?
- Analogous
- Incorrect try again
- Parametric
- Incorrect try again
- Bottom-Up
- Correct wonderful
- Activity-Based
- Incorrect try again
- Analogous
- Which of the following methods is associated with using average costs per unit based on costs from other projects?
- Analogous
- Incorrect try again
- Parametric
- Correct superb
- Bottom-Up
- Incorrect try again
- Activity-Based
- Incorrect try again
- Analogous
- When John based the estimate for his move on the cost of his friend's move, this was a/an
- Analogous estimate
- Correct perfect
- Parametric estimate
- Incorrect try again
- Bottom-up estimate
- Incorrect try again
- Activity-based estimate
- Incorrect try again
- Analogous estimate
- When Jane grouped her costings, e.g. friends' help, packing materials, rental truck, this was a/an
- Analogous estimate
- Incorrect try again
- Parametric estimate
- Incorrect try again
- Bottom-up estimate
- Incorrect try again
- Activity-based estimate
- Correct first class
- Analogous estimate
- When Jane prepared a detailed estimate of costs for packing materials and use of a rental truck, this was a/an
- Analogous estimate
- Incorrect try again
- Parametric estimate
- Incorrect try again
- Bottom-up estimate
- Correct Nice Job
- Activity-based estimate
- Incorrect try again
- Analogous estimate
- When the truck company estimated the size of the moving truck on the number of bedrooms, this was a/an
- Analogous estimate
- Incorrect try again
- Parametric estimate
- Correct Brilliant
- Bottom-up estimate
- Incorrect try again
- Activity-based estimate
- Incorrect try again
- Analogous estimate