Building and construction/Variations/FAQ's

From WikiEducator
Jump to: navigation, search


Icon key points.gif
Key points
FAQ's about Variations



1. Contracts will always include procedures for processing variations.

2. Variations can be created due to unforseen matters that could not reasonably be predicted by a competent and skilled contractor at the time the contract was entered in to. For example excavation work where the foundation is suspect or unknown.

3. If a variation is requested by the contractor due to an error on his behalf the owner should not be liable for an increase in the contract price.

4. Approved variations should be paid for at the time of the next progress payment after completion of the varied works.

5. It is not a requirement to get written approval for a variation if there is a danger to persons or a risk of damage to property if the work is not done immediately.