* Which of the following methods is associated with reorganising estimates by grouping with activity codes?
+
* Which of the following contract is most appropriate for a project whose scope is very clear and unlikely to change?
**Analogous
+
**Fixed-Price Contract
***'''Incorrect''' try again
+
***'''Correct''' Well done
**Parametric
+
**Cost-Reimbursable Contract
***'''Incorrect''' try again
+
***'''Incorrect''' Try again
**Bottom-Up
+
**Time and Materials Contract
***'''Incorrect''' try again
+
***'''Incorrect''' Try again
**Activity-Based
+
* Which of the following contract is most appropriate for a project that features high uncertainty and is likely to require numerous adjustments as more information is available?
***'''Correct''' well done
+
**Fixed-Price Contract
* Which of the following methods is associated with an estimate that is based on other project estimates?
+
***'''Incorrect''' Try again
**Analogous
+
**Cost-Reimbursable Contract
***'''Correct''' good job
+
***'''Incorrect''' Try again
**Parametric
+
**Time and Materials Contract
***'''Incorrect''' try again
+
***'''Correct''' Well done
**Bottom-Up
+
* Which of the following contract is most appropriate for a project whose scope and costs for performing the work are not well known?
***'''Incorrect''' try again
+
**Fixed-Price Contract
**Activity-Based
+
***'''Incorrect''' Try again
***'''Incorrect''' try again
+
**Cost-Reimbursable Contract
* Which of the following methods is associated with identifying the cost of each item in each activity of the project?  
+
***'''Correct''' Well done
**Analogous
+
**Time and Materials Contract
***'''Incorrect''' try again
+
***'''Incorrect''' Try again
**Parametric
+
 
***'''Incorrect''' try again
+
**Bottom-Up
+
***'''Correct''' wonderful
+
**Activity-Based
+
***'''Incorrect''' try again
+
* Which of the following methods is associated with using average costs per unit based on costs from other projects?  
+
**Analogous
+
***'''Incorrect''' try again
+
**Parametric
+
***'''Correct''' superb
+
**Bottom-Up
+
***'''Incorrect''' try again
+
**Activity-Based
+
***'''Incorrect''' try again
+
*When John based the estimate for his move on the cost of his friend's move, this was a/an
+
**Analogous estimate
+
***'''Correct''' perfect
+
**Parametric estimate
+
***'''Incorrect''' try again
+
**Bottom-up estimate
+
***'''Incorrect''' try again
+
**Activity-based estimate
+
***'''Incorrect''' try again
+
*When Jane grouped her costings, e.g. friends help, packing materials, rental truck, this was a/an
+
**Analogous estimate
+
***'''Incorrect''' try again
+
**Parametric estimate
+
***'''Incorrect''' try again
+
**Bottom-up estimate
+
***'''Incorrect''' try again
+
**Activity-based estimate
+
***'''Correct''' first class
+
*When Jane prepared a detailed estimate of costs for packing materials and use of a rental truck. this was a/an
+
**Analogous estimate
+
***'''Incorrect''' try again
+
**Parametric estimate
+
***'''Incorrect''' try again
+
**Bottom-up estimate
+
***'''Correct''' Nice Job
+
**Activity-based estimate
+
***'''Incorrect''' try again
+
*When the truck company estimated the size of the moving truck on the number of bedrooms, this was a/an
+
**Analogous estimate
+
***'''Incorrect''' try again
+
**Parametric estimate
+
***'''Correct''' Brilliant
+
**Bottom-up estimate
+
***'''Incorrect''' try again
+
**Activity-based estimate
+
***'''Incorrect''' try again
+
 
}}
 
}}

Revision as of 01:46, 5 October 2016

Icon qmark line.svg
Quiz

Test out what you have learnt in this fun quiz.

  • Which of the following contract is most appropriate for a project whose scope is very clear and unlikely to change?
    • Fixed-Price Contract
      • Correct Well done
    • Cost-Reimbursable Contract
      • Incorrect Try again
    • Time and Materials Contract
      • Incorrect Try again
  • Which of the following contract is most appropriate for a project that features high uncertainty and is likely to require numerous adjustments as more information is available?
    • Fixed-Price Contract
      • Incorrect Try again
    • Cost-Reimbursable Contract
      • Incorrect Try again
    • Time and Materials Contract
      • Correct Well done
  • Which of the following contract is most appropriate for a project whose scope and costs for performing the work are not well known?
    • Fixed-Price Contract
      • Incorrect Try again
    • Cost-Reimbursable Contract
      • Correct Well done
    • Time and Materials Contract
      • Incorrect Try again